Problem/Issue Statement
The current problem for Bombardier
is the two ERP inefficiencies with the Mirabel plant and the Saint-Laurent
location. While these locations were increasing with success, there were still
certain flaws that need to be fixed. Looking forward to the third ERP
installation the company simply needs to fix these flaws between its
implementation and the best practices regarding the consultants, press, and
companies.
The main problem is the
current disagreement between the project team and the company employees
regarding the validity of processes and the methodologies. When looking at the
symptoms we can see that there is an inefficient concentration of knowledge
with the users, project structure, and employees.
The current scope of
the problem is the ERP systems at Mirabel and Saint-Laurent along with the
locations where the ERP system will be implemented in the near future for
Bombardier. Bombardier is planning to switch from their current legacy system
to the ERP system, which will be an essential change to the company.
Situation
Assessment
The context of the problem is that Bombardier is one
of the leading manufacturers for aerospace and transportation, which they have
reported over $8 billion in 2007. Bombardier has realized that they have to
change their legacy system to an ERP system. The first test for the ERP system
at the Mirabel plant did not go so well because the users were frustrated due
to a lack of communication between the project team and the employees. However,
the second test went a lot more efficient as the trained employees were
prepared and the message was delivered from management to the employees in a
more understanding manor.
The decision criteria will and should determine a
solution for the ERP practices to be established. An efficient ERP
implementation of the 12 Best Practices should present as follows:
1. Executive management should endorse the ERP
project. Implementation by VPs sponsorship.
2. Executive management should remain actively
involved throughout the implementation. Implementation by executive policy
committees to ensure
project governance.
3. ERP software implementation responsibilities
should be shared between the IT department and functional areas where the
software is being
implemented. Implemented by policy committees
involving senior management and the implementation team consisting of IT
personnel.
4. Executive management should be cognizant about
the institution’s ability to adapt to the organizational changes that occur
when ERP software is
implemented. Implemented by being aware of Shock and
Shock Relief.
5. A project manager should be assigned the
full-time to the implementation.
6. The project team composition should represent all
functional areas where the software will be implemented. Implementation through
all systems.
7. Project team members’ normal job responsibilities
should be reassigned to other employees for the project duration.
8. Employees should receive training on how to work
as a team on a project before implementation begins.
9. The institution should retain ownership of the
implementation process. “Skills transfer” from consultant to company.
10. All employees who will use the software should
receive thorough training.
11. The institution should change its administrative
processes to fit the software. (Must be accepted to end users)
12. Implementation information should be
continuously communicated to the business community.
List/Evaluation of Plausible Alternatives Courses of Action
The possible course of action would be to change the
implementation process to the ERP best practice approach. Bombardier could make
multiple changes in the company’s approach or simply copy the approach that was
taken in the Saint-Laurent location without any major changes.
The first alternative that could be made is to
improve Best Practice 3 & 6. The current issue with these practices is the
lack of cohesion between Project Team and End Users along with a lack of
accuracy in progress reporting. The recommended action would be to include
function specialists in design and implementation activities, set in place
formal process for accurate & real time scorecard progress, and diversify
Support Team to include Super Users & function specialists along with IT.
The immediate impact that this would cause is an increased cohesion between
business and IT implementation, ensures deadlines are met and that there are
smoother transitions to the new system, decreased vision, and reduction in
costs.
The second alternative that could be made is to
improve Best Practice 9. The current issue with this practice is that currently
Bombardier is employing SAP developers who lack the Subject Matter Expertise to
provide internal support, which would require SAP support. Therefore the recommended
action would be to hire IT specialists on a full time basis who could phase out
the reliance on the consultants (SAP developers) who don’t specialize in this
specific function. The impact that this would have is reduction in costs
because the onboard employees would cost less than the consultants. The second
impact is that the usual problems that occur on a daily basis would be
immediately resolved because of the IT specialists.
The third alternative that could be made is to
improve Best Practice 11. The current issue with this practice is the current
disconnect between the contact management process and SAP system cost. The
recommended course of action is to establish a standardized contract process
and expand the SAP features to accommodate the improved process. This would
eliminate inefficiencies regarding costs while retaining partial low cost
contract savings, which simply would utilize the system more efficiently.
Recommendation
My recommendation before preparing for the
consultants’ presentation is to adopt the changes of the four practices based
upon their net impact. For Best Practice 3 & 6 Bombardier should include departmental specialists in design and
implementation activities, diversify Support
Team of Super Users and Departmental specialists along with IT, and set in
place formal process for accurate & real time scorecard progress. For Best
Practice 9 Bombardier should simply hire IT specialist’s experts on a full time
basis and phase out reliance on consultants (Certified SAP developers).
Regarding Best Practice 11, Bombardier should establish a broad but
standardized contract process and expand the SAP features to accommodate the
improved processes.
Presentation
The consultants’ presentation should
be very specific for which activities in the company’s implementations should
be changed to better fit the practices. It should also include a large amount of
information on each best practice that they have chosen for their standards. The
consulting team should explain all of the adjustments to the current policies
and state the costs of each one. They should also discuss the impact that this
would have along with the efficiency of each change. The consultants should
offer a fair view that states the improvements that could be made regarding the
Mirabel location. Overall the consultants should give a solid overview on all
of the practices along with which ones should be rectified.
Reflection
After looking over last night’s
presentation I still believe that Bombardier can take several steps to enhance
the implementation procedure. This is imminent after Bombardier stated the
first and second test of the ERP system a success. I am in agreement with the
consultant’s suggestion that the existing inefficiencies in the implementation
process should follow the best practices between the IT department and
functional areas pertaining to the software implementation, internal process,
and company ownership.
One of the most interesting parts
of the consultant’s presentation was the suggestion to hire IT specialist and
eliminate reliance on Bombardier’s consultants in order to increase the
consultant’s knowledge of the internal SAP’s. I can see how this is a possible
solution but I still believe that cycling the business employees occasionally
to the support team would be a more effective solution. The main inefficiency
with the consultant’s proposal is that I personally cannot comprehend how 3 SME’s
will effectively replace 400 SAP developers simply because of the workload.
Another key point that I found intriguing was the consultant’s illustration
of the problems regarding the contract management processes. I agree that
rewarding contract agents for negotiating cheaper contracts is inefficient due
to lengthier contract negotiations. I believe adopting a hybrid approach that
would standardize the process and expand SAP features would be effective
although I believe input from the contract agents would be ideal in order to
receive their thoughts on if this suggestion would resolve their complaints
about the new contract management procedures.
The final point that I found
intriguing is the consultant’s suggestions to include specialists regarding the
project management team in order enhance interactions between the project team
and the ends users pertaining to the implementation process. I agree with this
suggestion as it indicates that more internal employees would join the project
team to gain more knowledge of the situation so that it is not so heavily
focused on just a few individuals. Although I agree with this suggestion, I do,
however believe that the core costs of $560,000 indicated by the consultants
could be more than the actual result. Conversely, I believe this cost is worth
the two-month absence of the most efficient talent. Furthermore, the additional
costs of $11,000 indicated by the consultants is also a bit understated but
these specialists are extremely smart and valuable in which therefore
Bombardier would have to hire these specialists in order to operate
efficiently.
In conclusion, I agree with most of the suggestions
that were made by the consulting team. However, I would suggest that functional
specialists are included in the project management team in which they would be
trained before their movement. We should examine in more detail whether or not
hiring SME’s to replace the SAP’s would be the right decision as of course this
is a major factor and decision. Lastly, Bombardier should rectify the contract
management system by creating standardized processes and by expanding the SAP
structure after they consult with the contract agents. All of these factors
would conclude in a more efficient ERP implementation with the foundation of
the best practices, which will result in an overall satisfaction from Bombardier.